Project Phase

Project Summary

The city will construct a 6-foot sidewalk on both sides of 68th Street from the Arizona Canal to just south of Camelback Road. The project will provide a consistent paved sidewalk to improve pedestrian movement and safety along this corridor.

Project Information

Budget: $3,000,000

Sponsoring Division: Transportation

Funding Source: Transportation Sales Tax

Project Location: 68th Street from the Arizona Canal to Camelback Road

Contact Information

Transportation & Streets Department

480-312-7250
Transportation & Streets Department

Project Information

The project will include asphalt improvement on this segment of 68th Street and restriping on the street surface. The road will be restriped to its current lane configuration on one lane in each direction.

This project was created is in response to a citizen request and was added the city’s capital improvement plan by the City Council.

Public Outreach

A community public meeting was held on May 15 at Scottsdale Stadium. View the presentation that was given at the meeting to learn more about the project.

The city held one-on-one meetings with property owners whose homes front 68th Street in April 2024.

Tentative Project Schedule

  • Design: Summer 2023 – Winter 2024/25
  • Public Outreach: Spring - Winter 2024/25
  • Utility Relocations: Fall 2024 – Spring 2025
  • Construction Start: Spring 2025
  • Construction Complete: Winter 2025/26
Back to Top