Bond 2019

In November 2019, Scottsdale voters approved three Bond Questions, totaling $319 million for 58 projects. In February 2020, the City Council adopted an implementation plan to complete these projects over a ten-year period.

The follow projects were approved as part of the 2019 Bond Election.

Download Project List & Descriptions

Project List

Parks, Recreation and Senior Services - 14 Projects - $112.6M

CIP Project No.CIP Project TitleEstimated BudgetProject Status
2Add Splash Pad and Improve Walkways at McCormick-Stillman Railroad Park$917,207Complete
10Replace Tennis Court Surface at Indian School Park and Scottsdale Tennis Center$3,497,104Complete
13Expand Granite Reef Senior Center to Meet Demand for Adult Day Care Center$2,972,175Future Year
21Expand Via Linda Senior Center to Meet Demand for Senior Services$4,538,632Design
22Build New Swimming Pools and Replace Building at Cactus Pool$31,229,600Planning
24Install High Efficiency Sports Lighting at 4 Facilities$1,224,304Complete
25Replace Aging Buildings that Comprise Paiute Community Center$11,174,242Future Year
30Indian School Park Field 1 Lighting$696,072Complete
41Install Solar Heating System for Eldorado Pool$560,332Design
42Add a Dog Park to Thompson Peak Park$4,637,357Construction
53Build Multi-Use Sport Fields in the area of Bell Road$40,000,000Complete
55Build a 17-Acre Neighborhood Park at Ashler Hills Drive and 74th Way (Whisper Rock)$6,097,659Complete
60Double the Solar Power Generating Capacity at Appaloosa Library$39,688Design
61Purchase land, expand Pinnacle Peak Park parking lot, staff office and restrooms, renovate hiking trail and construct an interpretive trail$5,000,000Future Year


Community Spaces and Infrastructure - 20 Projects - $112.3M

CIP Project No.CIP Project TitleEstimated BudgetProject Status
1Replace Aging Infrastructure and Improve Public and Event Spaces on Civic Center Plaza$27,317,840Complete
15Build 200 Space Parking Lot off 75th Street to Serve the City Court and Scottsdale Stadium$1,530,709Design
18Build Roadway and Pedestrian Improvements along 2nd Street from Drinkwater Blvd to Goldwater Blvd$1,845,427Design
19Build Roadway and Pedestrian Improvements along Marshall Way North of Indian School Road$1,800,780Future Year
20Build Roadway and Pedestrian Improvements along Main Street from Scottsdale Road to Brown Avenue$994,180Future Year
23Repair Lakes and Irrigation at Vista del Camino Park in the Indian Bend Wash$23,512,804Construction
32Renovate and Modernize the Stage 2 Theater at the Scottsdale Center for the Performing Arts$1,200,000Future Year
43Improve 5th Avenue from Scottsdale Road to Goldwater Boulevard$3,569,857Planning
45Renovate WestWorld Horse Barns to Increase Rentable Space$4,702,972Construction
46Replace the Public Address System at WestWorld$366,132Complete
47Replace WestWorld Arena Lights to Reduce Operating Costs$1,331,273 Complete
48Widen 94th Street at WestWorld to Improve Access$1,469,153Planning
50Renovate Arena at WestWorld to Provide Flexible Event Space$960,298Complete
51Install Permanent Lighting at WestWorld Parking Lots to Reduce Operating Costs$1,438,293Planning
52Expand Restrooms in WestWorld North Hall$701,532Complete
57Install Solar Systems North Corporation Campus$4,810,300Complete
58Install Parasol Solar Shade Structure at City Hall Parking Lot$4,669,400Construction
59Install Solar Systems at Civic Center Campus$2,784,500Design
62Build a Bridge on Thompson Peak Parkway Bridge over Reata Pass Wash to Improve Safety$6,300,000Design
63Build Parking Structures in Old Town Scottsdale$20,962,800Design


Public Safety and Technology - 24 Projects - $94.1M

CIP Project No.CIP Project TitleEstimated BudgetProject Status
4Replace Outdated Emergency Response Equipment for Fire Department$2,057,000Complete
5Modernize Computer Equipment Rooms to Protect City Servers$691,600Construction
6Replace Emergency Power Source for Public Safety Radio Network$305,240Complete
7Replace Outdated 9-1-1 Computer Aided Dispatch and Records Management to Improve Efficiency$591,156Complete
8Replace Website Management Software$188,556Complete
9Install Fiber Optic Infrastructure to Reduce Operating Costs$11,385,555Construction
11Replace Document Management System to Improve Public Access to Information$674,000Complete
12Update Scottsdale's 15-year-old Digital Terrain Model$177,240Eliminated
14Replace Obsolete Planning and Permitting Software$2,964,000Implementation
16Replace the City's Obsolete Training Software$342,000Complete
17Obtain a Citywide Data Management and Analytics Solution for Data-Based Decision Making$62,000Implementation
26Replace Deteriorating Vehicle Training Track at the Police and Fire Training Facility$1,919,401Design
27Modernize and Expand the Police and Fire Training Facility$4,227,262Complete
28Build a New Fire Station near Hayden Road and the Loop 101 to Improve Response Times$10,470,043Complete
29Replace Workstations at 911 Communications Dispatch Center to Accommodate New Technology$638,522Complete
33Renovate the Via Linda Police Station to Increase Efficiency$16,600,000Construction
34Build New Fire Station at 90th Street and Via Linda to Replace Aging Facility$5,914,028Design
35Install Bullet Proof Glass in Reception Areas of Police Department Facilities$977,256Complete
36Provide Free Public WiFi at the Civic Center Plaza$57,200Complete
37Implement an Inventory and Asset Control System for City Technology$572,000Complete
38Build a new Fire Department Training Facility$18,258,520Complete
39Renovate the Foothills Police Station to Accommodate Current Staffing Levels$1,024,000Future Year
40Renovate and Expand the Civic Center Jail and Downtown Police Facility to Meet Demand$13,102,518Design
44Replacement of Fire Utility Truck to be used on fire ground activity and response to Hazardous Materials and Technical Rescue incidents$782,638Complete