Project Phase
Project Summary
Construction continues for improvements to Scottsdale Road from Jomax Road to Dixileta Drive. Planned improvements will convert this section of Scottsdale Road to a complete street to include landscaped medians, bike lanes, sidewalks and trails to improve safety, capacity and accessibility for motor vehicles, bicycles and pedestrians. The project includes the installation of a signalized crossing at Pinnacle Vista Drive, and drainage improvements.
Project Information
Budget: $43,685,237
Sponsoring Division: Transportation
Funding Source: Transportation Sales Tax
Additional Funding Sources: Maricopa Association of Governments Regional Sales Tax
Project Location: Scottsdale Road from Jomax Road to Dixileta Drive
Project Map: View Map
On April 8, the City Council gave direction to redesign the intersection improvements planned at Scottsdale Road and Dynamite Boulevard from a roundabout to a traditional signalized intersection. That redesign work is underway and staff are identifying potential impacts to the overall project schedule.
Construction began in the Spring of 2025 and the project is approximately 50 percent complete. Construction has been taking place both north and south of the Dynamite Blvd. intersection and this portion of the project is scheduled to be predominately complete this spring. Work on the redesigned interaction will begin in early 2026 and take place for the remainder of the year. The entire project will receive final paving and striping at the end of the project.
During construction, lane reductions and turn restrictions may be in place, as needed, to shift traffic away from the work zone. Please obey traffic signage as it is placed for the safety of residents, travelers and construction crews. Traffic control remains in place 24/7 to protect the work zone, and speed limits are reduced near the work zone. Work primarily takes place during daytime hours, weekdays; however, it may be necessary, at times, to conduct work during night hours or weekend days.
Project Information
Consistent with the City's Transportation Master Plan, this project will convert this section of Scottsdale Road to a complete street including updates to the major intersections, landscaped medians, bike lanes, sidewalks and trails to improve safety, capacity and accessibility for motor vehicles, bicycles and pedestrians.
This project will include the design of:
- 8-foot wide separated sidewalk on the west side
- 10-foot multi use path or 8-foot trail on the east side
- High intensity activated crosswalk (HAWK) crossing at Pinnacle Vista Drive
- 150-foot of right of way (targeted)
- Eliminate wet crossings
Take a look at images to see what the completed project will look like
Public Outreach
During the design process several meetings were held with homeowners' associations in the area and a public meeting was held with the community.
Project History
Project Schedule
Fall 2020 – Spring 2021 | Data Gathering Traffic Analysis Drainage Analysis Noise Analysis |
| Spring & Summer 2021 | Develop Preferred Alternative |
| October 2021 | Virtual Public Meeting #1 |
| Fall 2021 | Stakeholder & HOA Outreach |
| Fall 2021 | Initial Design |
| 2023/2024 | Public Hearing Process Final Design Right of Way Acquisitions Utility Relocations |
| 2024-2025 | Roadway Construction |
Frequently Asked Questions
- Will the speed limit on Scottsdale Road change?
- On Scottsdale Road the speed limit will remain 50 mph which is the current posted speed for most of the corridor.
- What are the traffic volumes on Scottsdale Road?
- 2019 Traffic volumes on Scottsdale Road between Jomax and Dynamite are 30,600 vehicles per day and between Dynamite and Dixileta are 27,200 vehicles per day. 2025 projected volumes for Jomax to Dynamite are 31,800 vehicles per day and for Dynamite to Dixileta are 28,600 vehicles per day.
- Has the city considered using rubberized asphalt to minimize road noise?
- The City's Public Works Division performed a noise study comparing rubberized and conventional asphalt and determined that there were no noticeable differences in noise abatement. Because rubberized asphalt costs significantly more than conventional asphalt and deteriorates approximately twice as fast, Scottsdale no longer uses it.
- Will there be raised median islands on Scottsdale Road?
- Yes, a raised landscaped median island will be constructed on Scottsdale Road, with openings at cross street intersections and property access points.
- What will the design do to improve drainage in the area?
- All of the at roadway grade wash crossings within this projects’ limits will be eliminated on Scottsdale Road. Scottsdale Road will have a pass-through drainage design for the regional flows at crossing locations. The peak storm flows will be collected in a swale on the east side of the roadway and directed to various culverts crossing beneath Scottsdale Road in their historic patterns.
- What types of sidewalks and trails will be built?
- The Scottsdale Road project will construct a new detached 8-foot concrete sidewalk on the west of the road and a new 10-foot concrete shared-use path on the east side of the road. Unpaved trails are also planned for the east and west sides of the roadway, which should be constructed shortly following the roadway improvements. The sidewalks, paths, and trails are consistent with other corridors in this part of the city and consistent with the city's complete streets policy, which encourages multi-modal transportation.
- What types of bike lanes will be built?
- A 5-foot bike lane is being constructed as part of the Scottsdale Road project that is consistent with city design and policy standards. The project will also install a detached 8-foot concrete sidewalk on the west of the road and a new 10-foot concrete shared-use path on the east side of the road.
- Will there be a wall or sound barrier installed along Scottsdale Road, and what would the wall look like?
- The results of the noise analysis indicated that future noise levels as a result of the improvements and increased traffic volumes will not meet the threshold for mitigation, therefore, sound barrier walls along Scottsdale Road are not warranted. Existing walls not in conflict with proposed improvements will be protected in place. Walls that do conflict with proposed improvements will be relocated, with the same height, aesthetics, finish, and color, beyond the conflict.
- How long will construction take?
- Utility relocations began mid-2024. Construction will begin in November 2024 and will be complete in late 2026.
- Will the roads be closed during construction?
- In general, a minimum of one lane of traffic in each direction will be open during construction. No long-term road closures are anticipated; however, short closures may be necessary to reconfigure traffic control and protect worker and public safety during project construction.
Project Hotline
480-898-4110