Find out where Certificate of Occupancy Certificates have been issued.
Upon passing a Final Inspection, a Certificate of Occupancy (C of O) is issued, allowing for the business to begin operation or a homeowner to move in.
The city's building code requires certain information to be included on the C of O. The most important item is the project address; the code also requires the name of the owner of the property at the time the certificate was issued. If during the process of construction the property ownership changes hands we can accept documentation to that fact and change the permit. The C of O stays with the property for perpetuity, even when owners come and go.
Find out where Certificate of Occupancy Certificates have been issued.
The issuance of a Temporary Certificate of Occupancy (TCO) allows temporary occupancy until the building is completed and a Final Certificate of Occupancy is issued.
For each Temporary Certificate of Occupancy issued, there will be required a refundable cash deposit or irrevocable letter of credit acceptable to the Building Official, paid to the city of Scottsdale to assure compliance to code and ordinance requirements. The amount of the cash deposit will be the same as the sum total of all permits issued to the project which includes foundation, building, electrical, mechanical and plumbing permit fees as specified in Scottsdale Revised Code, Chapter 31, Article VII, or two thousand five hundred dollars ($2,500.00), whichever is greater. Within 30 day of the issuance of the final certificate of occupancy, the deposit will be refunded less a $200.00 processing fee.
Step 1:
Required Inspections
Step 2:
Schedule 025
Step 3:
Approvals
Step 4:
Occupy
The following inspections need to be scheduled & approved prior to requesting the Temporary Certificate of Occupancy inspection:
These inspections must be requested and approved before requesting the 025.
When you get the above approvals, then schedule a 025 (Temporary C of O) inspection. Call 480-312-5750
After the 025 approval is received, the TCO will be issued.
Code | Inspection Type | Description |
---|---|---|
013 | TCO Off-Site | Completed By: Public Works Required on all Commercial, Multi-Family and SFR structures prior to the issuance of the TCO. Inspection to assure all offsite work (if any) is in compliance with MAG specification and approved plans. |
032 | TCO On-Site | Completed By: Building Inspections
Required on all Commercial, Multi-Family and SFR structures prior to the issuance of the TCO. Inspection to assure compliance with DRB stipulations and city approved plans. |
036 | TCO Fire |
Completed By: Fire Inspections |
037 | Backflow Preventer | Required on Commercial or Multi-Family
2 inspections required: 1st inspection - to check size, type, and location per city approved plans and to check the installation per city approved detail; 2nd inspection - to check testing and certification by an approved testing agency prior to issuance of either a TCO or FCO. |
025 | TCO | Building Inspection includes building, electrical, mechanical and plumbing inspections to assure compliance with city codes, city approved plans and amending ordinances. |
Last Updated: Jun 29, 2024
Holiday Name | Holiday Date | Observed On |
---|---|---|
Veteran's Day | Mon, Nov 11, 2024 | Mon, Nov 11, 2024 |
Thanksgiving Day | Thu, Nov 28, 2024 | Thu, Nov 28, 2024 |
Day after Thanksgiving Day | Fri, Nov 29, 2024 | Fri, Nov 29, 2024 |
Christmas Day | Wed, Dec 25, 2024 | Wed, Dec 25, 2024 |