Project Phase

Project Summary

Scottsdale is making a major investment to improve the quality and condition of streets, alleyways and parking lots in Old Town. When complete, business owners, residents and visitors will enjoy a smoother and safer driving experience and enhanced curb appeal. The city and our vendors work hard to meet construction timelines. However, weather, staffing and roadway conditions can delay a project. Please call the project hotline for schedule and phasing updates, 480-898-4100.

Project Information

Budget: $15,000,000

Sponsoring Division: Transportation

Funding Source: Other Funding Source

Additional Funding Sources: Transportation 0.2% Sales Tax

Project Location: Old Town Scottsdale

Project Hotline: 480-312-4444

Contact Information

Transportation and Infrastructure
480-312-7250
602-301-1325
Transportation and Infrastructure

The work will include a variety of pavement preservation improvements including crack fill, fog seal, micro seal and mill and overlay. The project began in June and will continue through October 2025 in numerous phases. Please see the project maps and schedule below to determine when work will be occurring in Old Town Scottsdale.

Current Paving Work

Mill and Overlay | Construction

Sept. 8-22 | Daytime Work | 5 a.m. – 5 p.m.

Mill and Overlay | Construction

Mill and Overlay | September 2025 | One Civic Center Parking Lot

Work is complete in the alleyways; businesses should expect to see crews completing minor repairs and utility adjustments over the next three weeks. The city's One Civic Center building parking lot, near Bennie Gonzalez Way and 75th St., is scheduled to be repaved Sept. 10-26. The lot will be closed, with limited access during construction. Additional visitor parking will be designated on Bennie Gonzalez Way.

Mill and Overlay | September 2025 | One Civic Center Parking Lot

Micro Seal Project | Project Extended to Sept. 10 | Overnight Work | 9 p.m. to 6 a.m.

Old Town Paving 4040 SOUTH

Micro Seal Project | Project Extended to Sept. 10 | Overnight Work | 9 p.m. to 6 a.m.

Upcoming Paving Work

Crack Seal

Crack fill is the process of applying asphalt emulsion into cracked and damaged surfaces on roads, alleys and parking lots. The process helps restore structural integrity and prevents moisture from penetrating the subbase.

Crack fill is applied quickly; crews work out of a moving truck using a hose to insert the material into cracks and a broom or squeegee to level the material. You may experience a momentary lane delay or alley closure; however the material dries quickly, and you will be able to drive over the surface within minutes of application.

Project IDDescriptionContractorWork Dates
2077Business streets between Scottsdale Road and Drinkwater, 2nd St. and Indian School RoadMr TannerCOMPLETE
3162Local Streets between Thomas Road and Osborn Road, Scottsdale Road to Miller RoadMr TannerCOMPLETE
3168Brown Ave. between Osborn Road and 2nd St.Mr TannerCOMPLETE
31935th Ave. between Indian School Road and Scottsdale Road (Excluding Goldwater intersection)Mr TannerCOMPLETE
4033Parking lots and Alleys. 2nd St. to Indian School, 69th St. to Scottsdale RoadMr TannerCOMPLETE
4034Alleys from Scottsdale Road to Miller Road, 2nd St. to Indian School RoadMr TannerCOMPLETE
4033Alleys and Parking Lots in QS 16-44. 68th St. to Scottsdale, Osborn Road to Indian School RoadNesbittTBD
4034Select Roadways in QS 16-45. Scottsdale Road to Miller Road, Osborn Road to Indian School RoadNesbittTBD
4039Alleys and Parking Lots in QS 17-44. 68th St. to Scottsdale Road, Indian School Road to Camelback RoadNesbittTBD
4039Select Roadways in QS 17-44. 68th St. to Scottsdale Road, Indian School Road to Camelback RoadNesbittTBD
3358Business Streets between Goldwater and Scottsdale Road, 2nd St. to Indian School RoadSWSSCOMPLETE
4033Parking Lots and Alleys. 2nd St. to Indian School, Goldwater to Scottsdale RoadSWSSCOMPLETE
4034Select Streets in QS 16-45. Osborn Road to Indian School Road, Scottsdale Road to Miller RoadSWSSCOMPLETE
4034Select Alleys and Parking Lots in QS 16-45. Osborn Road to Indian School Road, Scottsdale Road to Miller RoadSWSSCOMPLETE
4039Select Streets in QS 17-44. Indian School Road to Camelback Road, 68th St. to Scottsdale RoadSWSSCOMPLETE
4039Select Alleys and Parking Lots in QS 17-44. Indian School Road to Camelback Road, 68th St. to Scottsdale RoadSWSSCOMPLETE
4040Select Streets in QS 17-45. Scottsdale Road to Miller Road, Indian School Road to Camelback RoadSWSSCOMPLETE
4040Select Alleys and Parking Lots in QS 17-45. Scottsdale Road to Miller Road, Indian School Road to Camelback RoadSWSSCOMPLETE
4033Select Local/Business Streets between 68th St. and Scottsdale Road, Osborn Road to Indian School RoadTalisTBD

Fog Seal

Fog seal is a pavement conditioner that helps protect roadways from environmental conditions while improving the overall appearance of the surface.

Fog seal is applied quickly; crews work out of a moving truck applying a thin layer of asphalt emulsion to asphalt surfaces. Expect to see road restrictions and alley and parking lot closures during fog seal application. The coating is dry and ready for vehicle and foot traffic in one to three hours after the final coat. Most of this work will be done at night to have the least amount of impact on surrounding businesses.

Project IDDescriptionContractorWork Dates
2077Business streets between Scottsdale Road and Drinkwater, 2nd St. and Indian School RoadMr TannerCOMPLETE
3162Local Streets between Thomas Road and Osborn Road, Scottsdale Road to Miller RoadMr TannerTBD
3168Brown Ave. between Osborn Road and 2nd StMr TannerTBD
31935th Ave. between Indian School Road and Scottsdale Road (Excluding Goldwater intersection)Mr TannerTBD
4033Parking lots and Alleys. 2nd St. to Indian School, 69th St. to Scottsdale RoadMr TannerCOMPLETE
4034Alleys from Scottsdale Road to Miller Road, 2nd St. to Indian School RoadMr TannerCOMPLETE
4033Alleys and Parking Lots in QS 16-44. 68th St. to Scottsdale, Osborn Road to Indian School RoadNesbittTBD
4034Select Roadways in QS 16-45. Scottsdale Road to Miller Road, Osborn Road to Indian School RoadNesbittTBD
4039Select Roadways in QS 17-44. 68th St. to Scottsdale Road, Indian School Road to Camelback RoadNesbittTBD
4039Alleys and Parking Lots in QS 17-44. 68th St. to Scottsdale Road, Indian School Road to Camelback RoadNesbittTBD
4040Selected Roadways in QS 17-45. Scottsdale Road to Miller Road, Indian School Road to Camelback RoadNesbittTBD

Micro Seal

Micro seal pavement preservation treatments help extend the life of asphalt streets and reduce maintenance costs. Additional benefits include a smoother and safer ride.

Expect to see lane restrictions, alley closures and parking lot closures during construction. Crews operate heavy equipment and often work with off-duty police officers to help direct traffic around the work area. Lane lines and parking lot symbols will be obliterated at the start of the project; refreshed lane markings will be applied at the end of the project. Micro seal surfaces are typically open to foot traffic within a half hour after application and vehicular traffic within four hours of application. You will receive additional notification if a micro seal project is occurring near you with specific time, dates and restrictions.

Project IDDescriptionContractorWork Dates
3358Business Streets between Goldwater and Scottsdale Road, 2nd St. to Indian School RoadSWSSCOMPLETE
4033Parking Lots and Alleys. 2nd St. to Indian School, Goldwater to Scottsdale RoadSWSSCOMPLETE
4034Select Streets in QS 16-45. Osborn Road to Indian School Road, Scottsdale Road to Miller RoadSWSSTBD
4034Select Alleys and Parking Lots in QS 16-45. Osborn Road to Indian School Road, Scottsdale Road to Miller RoadSWSSTBD
4039Select Streets in QS 17-44. Indian School Road to Camelback Road, 68th St. to Scottsdale RoadSWSSCOMPLETE
4039Select Alleys and Parking Lots in QS 17-44. Indian School Road to Camelback Road, 68th St. to Scottsdale RoadSWSSCOMPLETE
4040Select Streets in QS 17-45. Scottsdale Road to Miller Road, Indian School Road to Camelback RoadSWSSAug. 24-Sept. 10*
4040Select Alleys and Parking Lots in QS 17-45. Scottsdale Road to Miller Road, Indian School Road to Camelback RoadSWSSAug. 24-Sept. 10*
4033Select Local/Business Streets between 68th St. and Scottsdale Road, Osborn Road to Indian School RoadTalisTBD

Mill and Overlay

A mill and overlay is the most extensive approach to asphalt maintenance and is utilized when surfaces have reached the end of their life and preventative treatments are no longer beneficial.

Expect to see lane restrictions, alley closures and parking lot closures during a mill and overlay project. These projects require significant heavy equipment, and you may see large dump trucks staging in areas adjacent to the construction area. The asphalt cures quickly and is typically ready for foot traffic in only a few hours and ready for vehicular traffic in 24 hours. You will receive additional notification if a micro seal project is occurring near you with specific time, dates and restrictions.

Project IDDescriptionContractorWork Dates
4033Parking lots and Alleys. 2nd St. to Indian School, 69th St. to Scottsdale RoadMr TannerCOMPLETE
4034Parking lots and Alleys. 2nd St. to Indian School, 69th St. to Scottsdale RoadMr TannerCOMPLETE
4033Alleys and Parking Lots in QS 16-44. 68th St. to Scottsdale and Osborn Road to Indian School RoadNesbittTBD
4034Select Roadways in QS 16-45. Scottsdale Road to Miller Road, Osborn Road to Indian School RoadNesbittTBD
4039Alleys and Parking Lots in QS 17-44. 68th St. to Scottsdale Road, Indian School Road to Camelback RoadNesbittSept. 8-22
4040Alleys and Parking Lots in QS 17-45. Scottsdale Road to Miller Road, Indian School Road to Camelback RoadNesbittTBD
4040Selected Roadways in QS 17-45. Scottsdale Road to Miller Road, Indian School Road to Camelback RoadNesbittTBD

Visit pavement preservation to learn more about what we do as a city to maintain our streets and about each of the preservation techniques.

Construction Information

Here’s what you can expect during construction:

Utility Adjustments

To avoid interruption of underground utility services, in-street utilities will be lowered at the start of the project and readjusted back to street level at the end of the project. This work moves quickly and will minimally impact property access.

Work Hours

Typically overnight work hours are 9 p.m. to 6 a.m., daytime work hours are 6 a.m. to 4 p.m.

Street Restrictions

Roads will be restricted but not closed during construction. Please plan ahead and follow detour signs when traveling near work areas.

Parking Lot Closures

Parking lots may be closed during construction. Please make alternative arrangements for deliveries, employee and customer parking.

Alley Closures

Alleys, and parking lots off alleys, may be closed during construction. Please make alternate arrangements for deliveries, employee and customer parking.

Trash Collection

Alleys will be closed to vehicle and foot traffic during construction; this may impact trash collection behind your business. Some containers may be temporarily relocated to nearby vacant areas or parking lots; some businesses may be directed to use shared containers during construction.

Containers in the construction area will be serviced daily between 5:30 - 6:30 a.m. Private companies should be able to provide uninterrupted service and have been notified about the early morning pick-up schedule. All containers will be placed back in their normal locations at the end of construction.

Back to Top